UPDATED - 29 JUL 2004

Click here for the latest about Cascade Mtn.

 

NOTE THAT SOME OF THE LARGER IMAGES BELOW ARE MISSING AT THIS TIME

The Arkansas Sky - Cascade Mountain Observatory to begin groundwork on April Fools Day!

The new building for the 16 inch Newtonian will begin groundwork in the morning at Cascade Mountain.  A 12x24 foot concrete pad will be poured and pier formed.  The pier will consist of a large substructure below the floor level and a 12 inch diameter column rising to 32 inches above the floor for placement of the large German Equatorial mount.  Initially, a 12x12 foot section of the pad will be used for the actual building at one end with plans to add another 12x12 foot control facility later in the year once the layout needs are determined.  Construction of the building should begin by early next week.  The building will feature a conventional "roll-back" roof on the observing room.

The 16" scope will be used to observe/image and report several specific objects including NEO's, asteroids, and comets as a nightly routine, but also variable star and planetary studies as the need arises.  

We are proud to have two new facilities in the works, and hope to double our contribution to photometric and astrometric data to Harvard, JPL and other data collection facilities each morning.  

Click on any thumbnail image below for a full size image (640x480)

April 1, 2003

Grounds looking south 
over ridge.

Looking east.

 

Update - April 2, 2003

The 12" diameter concrete pier is nearly complete with several thousand pounds of substructure.  The 12x24 pad is ready to pour in the morning.

04010001.JPG (68616 bytes)

Looking South

12" pier form

Another view looking East with one the of observatory supervisors inspecting the work.

There are still several trees that will have to come down to gain good views in all directions.  The location was placed slightly down a gradual slope from the ridge to locate it some distance from the ridge road.  

 

Update - April 3, 2003

04020003.JPG (118776 bytes)
Getting ready to fill the pier form
04020005.JPG (108868 bytes) 04020008.JPG (66931 bytes)
Watching the azimuth alignment
04020014.JPG (109250 bytes) 04020015.JPG (103449 bytes)
Last minute check on level
04020016.JPG (105488 bytes) 04020018.JPG (114100 bytes)


Update - April 16, 2003

The frame and outside walls are now complete for the 12x12 observing room section.  No window has been installed as yet.  The 12x12 office will be built later in the year on the WEST end where the door currently is.  The roof trusses can be seen in the background laying on the concrete slab.  I hope to have the roll-back roof installed by next week.  The roof will roll back to the East (left in the two exterior photos).

04160036.jpg (73562 bytes)

 

04160038.jpg (61036 bytes)

 

04160039.JPG (44168 bytes)

Looking in the door.  Mount and pier covered in center of room.  OTA remvoved.

I plan to finish the interior myself and wire the building for electricity.   

 

Update June 21, 2003

After a long delay work has resumed on the observatory.  Dave Birmingham came on June 7 and helped greatly in getting the roof structure built.  
Thanks Dave!  

The roof trusses have been installed on the rolling frame and the external roof support structure has been completed (6/21/2003).  Only the roofing itself, gable ends, and soffits are left to complete the outside.

06070001.jpg (149721 bytes) 06070002.jpg (70603 bytes) 06070004.jpg (152703 bytes)

06070005.jpg (139670 bytes)
Our supervisors Ben and "Tiny"

06070008.jpg (155902 bytes)

06070010.jpg (160308 bytes)
Close up of the rail system with the iron "V" groove wheels w/roller bearings, and angle iron tracks. 

06070012.jpg (153328 bytes) 06070015.jpg (52277 bytes) 06070021.jpg (152148 bytes) 06070024.jpg (154513 bytes)

06210001.jpg (145891 bytes)

06210002.jpg (149784 bytes) 06210003.jpg (150100 bytes) 06210004.jpg (147659 bytes) 06210005.jpg (145426 bytes)

 

Update June 29th

Almost near completion.  A few minor things left to do such as installing the soffits, weatherproofing the gables, etc.  I began to install the electrical wiring today and the main panel can be seen in the front.  I will be running a 100 amp service, but probably will never use more than 30 amps at one time.  Still a lot of cleaning up to do around the building.

The roof rolls as smooth as silk with no binding whatsoever.  One man can easily open or close the structure due to the grooved steel wheels with tapered roller bearings riding on inverted angle iron.  Roof is secured to the building when closed with large turnbuckles and threaded steel rods.

Click on any image below for a full size photo.

06290001.jpg (103660 bytes)
Front

06290003.jpg (51947 bytes)
A view of the steel "v" groove wheels and track.

06290006.jpg (47766 bytes)
One of the wheels taken from the inside where the grease fitting is accessible.

06290007.jpg (123398 bytes)
Side view with roof partially open.

06290008.jpg (106840 bytes)

06290010.jpg (98732 bytes)

vgroove.jpg (23511 bytes)
Steel "V" groove wheel w/roller bearings.  Each wheel has a capacity of 500 lbs.  There are four of these on each side of the roof.

vgplan.jpg (64382 bytes)
My original plan of the wheel support structure and iron rail.

 

Update Feb. 7th, 2004

A new massive German Equatorial mount from AB Engineering will hold the OTA.  Click on the PDF file to see detailed views of the new mount.  This mount will use a 15" gear on the RA axis, and the 11.5" Aeroquest gear on the Declination axis.  Mount will be full GOTO and capable of semi-robotic remote operation.

PDF of GEM Details - Click Here

B. Morgan Sherrod

--------------
Crystal Clear Nights!
B. Morgan Sherrod - Staff, ASO

Arkansas Sky Observatory
Cascade Mountain


Back to ASO

Copyright Arkansas Sky Observatory © 2003  [A.S.O.] All rights reserved. Revised: